Double Girder Overhead Crane Site Acceptance and Handover Checklist
Date: 2026-11-26 Share:
Double Girder Overhead Crane Site Acceptance should determine if the crane installed matches the approved project requirements and is acceptable for operation. Evidence should address runway interface, electrical readiness, functional performance, project-specified load test, resolution of defects, and handover for operations.
Mere movement of the hook will not be sufficient to accept the crane. The purchasing team requires signed documentation as to what was done, for which requirement, by whom, and the outcome. Each unresolved item needs a responsible owner and impact on release.

Define the Acceptance Basis Before Testing
Review the site acceptance test plan before assembling witnesses or test weights. Note the crane serial number, crane configuration, drawing revisions, requirements, test procedures, acceptance criteria, and signing authorities.
Distinguish energization authority, loading tests authority, and production authority. They each need their own justification. Contractual acceptance and payment issues should not be confused with safe-operation authority.
OSHA 1910.179 deals with inspection and testing for US general industry installations in its jurisdiction. The design and construction team needs to specify all the requirements involved; a purchase order checklist does not excuse them.
FAT vs Site Acceptance Testing
Factory acceptance testing verifies agreed equipment and functions before shipment within the factory test arrangement. Site acceptance verifies the erected crane on its actual runway, permanent power supply, and final control interfaces.
The separate double girder overhead crane FAT guide covers the factory stage. Transfer every deferred FAT item into the site register with its original reference, closure evidence, and responsible party. A shipment-release signature does not close installation-dependent checks.
Overhead Crane Site Acceptance Checklist
Use the following sequence as a project checklist framework. Record the requirement reference, measured result, instrument identification, attachments, date, and signatures for each applicable item. Mark exclusions with an approved reason.
Verify Runway and Rail Interfaces
Compare the as-installed runway survey with approved crane and building-interface drawings. Check rail gauge, alignment, elevation, joints, fixings, end stops, and the crane’s operating and maintenance clearances against project criteria.
Runway errors can cause skewing, flange contact, vibration, and uneven wheel loading. Increasing drive power or adjusting controls should not substitute for identifying a mechanical interface defect.
Request these records before releasing the interface:
- Survey results with measurement locations, datum, instrument details, and applicable tolerances.
- Rail-fixing and structural-connection inspection records, including specified bolt-tightening evidence.
- Confirmation that the supporting structure was reviewed for the approved wheel loads and test conditions.
- Clearance checks covering the bridge, trolley, hook envelope, power collectors, and access routes.
The runway contractor supplies installation evidence. The responsible structural engineer reviews supporting-structure matters, while the crane supplier confirms equipment-interface requirements. The owner’s designated representative records interface acceptance.
Complete Checks Before Energization
Authorized electrical personnel should verify the supply characteristics, isolation arrangements, protective bonding, cable terminations, protection settings, and wiring against approved diagrams. Record insulation and continuity tests using methods suitable for the installed electronics.
Inspect conductor rails, collectors, festoon movement, cable supports, cabinet cleanliness, guards, and equipment identification. Confirm that mechanical assembly, rope reeving, lubrication, access protection, and removal of installation tools are complete.
The electrical contractor produces test records; the commissioning lead checks readiness. The site authority responsible for energization releases permanent power only after the relevant mechanical, electrical, and site-safety prerequisites are satisfied.
Witness Functional Verification
Begin with controlled no-load tests under the approved procedure. Verify hoisting, trolley travel, bridge travel, direction labels, specified speed modes, braking response, and control-station selection.
Test emergency stops, travel limits, hoist limits, alarms, interlocks, and installed protective functions. Include radio-signal loss, anti-collision, overload protection, or attachment interfaces where specified, using the manufacturer’s approved test methods.
Record the expected response and actual result for each function. “Safety devices checked” is insufficient: the report should identify the device, triggering condition, resulting motion inhibition, and reset behavior.
The commissioning team executes the tests, and the owner or appointed inspector witnesses agreed points. Unexpected movement, brake slip, or failed protection requires investigation and corrective action before progression.
Perform Project-Defined Load Tests
Confirm the test conditions with the project designer, crane manufacturer, applicable requirements, and approved procedure. Specify the load, rigging allowance, trolley positions, travel scope, speeds, hold periods, measurements, and stopping criteria.
Do not copy load percentages, holding times, or deflection ratios from another project or a factory article. Test conditions must be compatible with the crane, runway, supporting structure, lifting accessories, and site restrictions.
Before testing, confirm:
- Traceable test-load identification and mass verification.
- Suitable lifting accessories and an approved rigging arrangement.
- Valid calibration records for the instruments used.
- Defined exclusion zones, communications, witnesses, and test supervision.
- Approved criteria for braking, structural response, and post-test inspection.
The signed report should identify actual loads and positions, readings, observations, deviations, and results. Retain any required measurements after unloading. The appointed test organization executes its assigned scope; the responsible engineer reviews structural questions and departures from the procedure.
Verify the Operating Environment
Record ambient conditions during testing and compare them with the design envelope. A short trial in mild weather cannot establish performance at temperature extremes.
For a High Temperature Crane, verify specified shielding, cooling, temperature monitoring, and protective responses. For a Low Temperature Crane, verify specified heaters, condensation controls, lubricant suitability, and cold-start provisions.
Check Crane Motor ratings, cooling arrangements, sensor wiring, and drive settings against the approved component schedule. Any seasonal verification still required should have an agreed method, date, owner, and effect on operating release.
Crane Commissioning Documents
Build an indexed dossier that identifies the installed equipment and final revisions. For a double girder overhead crane, document consistency matters: the nameplate, hoist arrangement, drawings, software settings, and test reports must describe the same configuration.
The handover register should include:
- Approved specifications, deviations, as-built drawings, and electrical schematics.
- Runway surveys, installation inspections, electrical test records, and energization release.
- FAT records, transferred open items, functional reports, load-test reports, and calibration evidence.
- Final drive parameters, control backups, access arrangements, and safety-device settings.
- Operating manuals, maintenance instructions, inspection schedules, and spare-parts lists.
- Training records, warranty terms, service contacts, and signed defect-closure evidence.
Nante Crane publishes installation and commissioning support within its project lifecycle services. Buyers should confirm the contracted attendance, documentation deliverables, and division of work rather than assuming the equipment order includes every site activity.
Maintenance staff should review Crane Lubrication requirements before handover. Record lubricant grades, application points, initial fill or lubrication status, and manufacturer-defined intervals. Assign responsibility for the first maintenance tasks so commissioning work connects to routine care.
Crane Handover Responsibility Matrix
Adapt this example to the contract. Name individuals and organizations, identify mandatory independent inspections, and distinguish execution from technical approval and owner acceptance.
| Activity | Produces or executes | Reviews or accepts | Required evidence |
| Runway interface | Runway contractor | Structural engineer and owner; supplier confirms crane interface | Survey and interface release |
| Energization | Electrical contractor | Authorized site electrical authority | Electrical tests and power release |
| Functional tests | Commissioning team | Owner or appointed witness | Signed device-by-device results |
| Load tests | Appointed test team | Required inspector and owner; engineer reviews design matters | Approved procedure and test report |
| Defect closure | Assigned corrective-action owner | Relevant technical reviewer and owner | Repair evidence and retest |
| Operating handover | Supplier and installation team | Owner’s operations and maintenance representatives | Dossier, training, and release certificate |
Before the acceptance meeting, circulate the evidence index and highlight missing records. An unsigned report, obsolete drawing, or unexplained deviation should remain visible in the register. Agree how document revisions will be distributed after closeout, including which copies operations and maintenance will retain as the controlled baseline.
Witness attendance does not transfer the installer’s obligations or replace statutory duties. Record who can stop testing and who can authorize restart after a defect.
Close Defects Before Operating Handover
Give each punch-list item a unique number, location, requirement reference, risk classification, owner, deadline, and closure method. Attach photographs, revised documents, or retest results as appropriate.
Safety-critical deficiencies must be corrected before operation. Any permitted minor outstanding work needs explicit owner acceptance, restrictions where relevant, and a completion date. Document affected functions and repeat the necessary checks after repairs or parameter changes.
FAQ
Can a Successful FAT Replace Site Acceptance?
No. Factory evidence cannot establish final runway geometry, site wiring, or installed clearances. Retain both records and connect deferred items.
What Makes a Handover Complete?
Required tests have passed, release-blocking defects are closed, applicable approvals are available, personnel have received agreed training, and operations and maintenance representatives have accepted the dossier and responsibilities.
Prepare a Project-Specific Commissioning Review
Purchasing managers and EPC teams can submit capacity, span, lift, site layout, runway survey status, power supply, environment, installation scope, applicable requirements, and target commissioning date. Include the proposed acceptance plan and unresolved interfaces so Nante Crane can review the required installation and commissioning support. Submit these details to request a project-specific commissioning scope review.